The new track and field facility at Spearfish Middle School is entering its final stages of construction.
Spearfish School District Superintendent Nick Gottlob says crews are expected to begin laying asphalt on the track this week, with installation of the artificial turf field to follow shortly afterward.
The project replaces a more than 30-year-old track and field complex that suffered from cracking pavement, drainage problems, and deteriorating soil conditions.
On Monday, the Spearfish School Board approved a nearly $60,000 change order to add two additional jumping pits and a runway. District officials say the additions are necessary if the facility is to host middle school and high school track meets efficiently.
The overall project cost is now approximately $2.8 million, and substantial completion of the facility is expected around September 10th.